Ive always wanted to do this, make my ultimate room, so i will over the following pages define and go through whats been done and give pictures along route so everyone can see.
So basically , moved into a new place after the divorce

and girlfriend has ok'd the lounge to be a cinema room. the lounge is about 21 ft x 11.5 ft (sorry i work in old money)
Only problem is a bloody great big fireplace on one of the walls, its about 4 foot wide by 2 ft deep and has smaller brickj plinths on either side, major eye sore. So ive had the builders in to remove this. Had a quote off several firms and have applied for a building notice off the council.
quotes are in and the work is under way.
First I wanted a greater amount of sockets tied into the ring mains to spread the load but i also wanted several of them to be on a single isolator switch so i could turn them off with ease at night. all done adn looking good
Ive also had 4 cat 5e cables run from the lounge upto the loft which ive got a 16 port netgear switch distributes the network around the house.
So the builders are taking the old chimney out and were going to support the upper part of the chimney with galllows brackets and hangers. The chimney is made of poured concrete and problem is halfway through and the building inspector now wants 2 new RSJ in to support everything, it also means 1 wall has to be knocked through and rebuilt using high density bricks to support the RSJ. The ceiling has to be pulled to get the RSJs in and the joists moved over to the new RSJ, basically loads more work has to be done or it wont be signed off.
My first question to all those in the know and i know ive been long winded about this, but if ive been quoted for a job i.e removal of a chimney and been given a price, if the job changes and becomes more involved and can i hold the builders to the original quote or do i have to suck it up and just pay out.
Shouldnt the builders have sized up the job correctly in the first place, they're argument was until things had been opened up your couldnt tell the magnitude fo the job.
Any help guys
ive got 9 days until the lease runs out on my rented place and the hose looks like a tornados hit it, literally